Client: Nuclear Electric PLC
Programme: 1987 – 1995 (our involvement)
Value: £3.6 billion (base date 2009)
Sector: Energy – Power generation (low carbon), nuclear new build
Description
- The first and currently the only PWR nuclear power station delivering 1200MW.
- Procurement route - Traditional route prevailing between 1987 to 1992. Various contract forms were used depending on the size and type of packages (i.e. ICE, Design & Build and GMP target price contract).
The Challenge
- Procure the contract in a “first of kind” environment.
- Manage and procure a large number of contractors on differing forms of contract.
- Manage design creep and design interfaces between the work packages.
- Eliminating cost risks.
- Control the costs to a defined budget.
The Solution
- Developed individual estimates for each civil engineering project.
- Pre and post cost management services for the construction of the civils structures, reactor plant, turbines, main cabling, cooling water works, controls and instrumentation, radioactive waste and HVAC plant.
- Developed innovative approaches to complex contractual structures.
- Integrated value engineering studies to ensure value for money.
- Developed rigorous project controls, cost reporting and change control systems.
The Results
- Politically sensitive project delivered on time and within the budget and contingency provisions set by Her Majesty’s Government, despite complex procurement of significant supply chain (60 contractors & 3000 suppliers).
The Lesson
- Strong visible leadership team required at the highest levels.
- Clear basis of understanding between client and contractor will ensure a successful project.
- Bring key contractors/consultants/designers on board early.
- Ensure that specific supply chain and procurement processes and procedures are in place early.
- Consolidate the form of contract to one suite of contracts.